Project case study · CS-10 · Land development · Stormwater BMP
Wildwood Commons
WhiteHorse Development Corporation · City of Willernie, Minnesota, USA · 2006. The first project in the seven-county Minnesota metro to rely on a single BMP for all of a site's stormwater, on a contaminated infill lot beside a wetland.
- Reference
- CS-10
- Edition
- 2 · September 2026
- Format
- PDF · 4 pages · 0.4 MB
- Access
- Open
About this case study
Two townhome buildings with nine units in all, on a 30,000 sq ft infill lot in Willernie, Minnesota. They were built in 2006 with EPIC in every green area as the site's only stormwater management system, collecting, treating and storing the runoff from the whole development.
The lot was once a gas station and an engine repair shop. It sits on the boundary between two cities, in a watershed that drains toward White Bear Lake, and a large wetland wraps around its north-east corner. Opposition focused on stormwater and the wetland, including concern that infiltration would carry pollutants into the water. Contamination was found during the works and cleaned up by TetraTech, Inc. with the MPCA. The site was below the Rice Creek Watershed District's one-acre permit threshold, but the developer met the standard anyway.
Stormwater from the roofs, roads and rear driveways is filtered and treated through the sand and reused for irrigation. Any excess drains through 4-inch PVC storm lines to an existing street catch basin. Irrigation works by gravity, with no pumps and nothing to prepare for winter or summer. At its normal water level the system holds up to three weeks of irrigation water. On this site the EPDM liner deliberately prevents infiltration, sealing the cleaned-up soil so contaminants cannot leach toward the wetland or groundwater.
Site performance was published as a modelled baseline compared with the system's actual outflow. From 16 June to 24 September 2007, with 13.55 in of rain, modelled runoff was 32,181 cubic feet and actual outflow was 14,172, a 56% reduction. For total phosphorus from 11 August to 20 September, the paper gives a modelled load of 0.2 lbs and an outflow of 0.019 lbs, and states an 85% reduction.
Project record
- Developer
- WhiteHorse Development Corporation; Mr Tim Jawor, President
- Location
- McGregor Avenue × Stillwater Road (Wildwood / CSAH 12), City of Willernie, Minnesota
- Constructed
- 2006
- Development
- Two townhome buildings, nine units total
- Site
- 30,000 sq ft former gas station and engine repair lot; site plan: ¾ acre, 80% impervious, adjacent wetlands
- Prior use
- A gas station and an engine repair shop
- Jurisdictions
- City of Willernie, Willernie City Engineer Mr Les Mateffy, Rice Creek Watershed District, Washington County, MPCA
- Receiving water
- Drains toward White Bear Lake, Minnesota
- Engineering
- RESI engineered the project and managed the approval process
- Site runoff, 16 June to 24 September 2007
- Precipitation 13.55 in · potential runoff 32,181 cu ft · EPIC actual outflow 14,172 cu ft · 56% reduction
- Total phosphorus, 11 August to 20 September
- Potential load 0.2 lbs · EPIC outflow 0.019 lbs · 85% total reduction, as given in the engineer's paper