Project case study · CS-06 · Municipal landscape · Saline remediation
Al Fanateer Corniche
Royal Commission for Jubail & Yanbu · Jubail Industrial City, Saudi Arabia. A 400 m² plot that the client monitored against a 50% saving target. The sand it was built with was too salty for turf, so the system flushed itself.
- Reference
- CS-06
- Edition
- 2 · September 2026
- Format
- PDF · 4 pages · 0.7 MB
- Access
- Open
About this case study
A 400 m² turf plot irrigated with treated sewage effluent at Al Fanateer Corniche, Jubail Industrial City. It was installed in December 2011 as a pilot for the Royal Commission for Jubail & Yanbu and monitored by the Commission's contractor SATCO together with EPIC staff on site.
In October 2011 Sheikh Faisal Al Rasheed, the Commission's Director of Planning, invited EPIC to run the pilot, with a target of a 50% water saving against existing systems. The site was against it from the start. The sand was very salty and unwashed, the turf supplied was of poor quality, and planting fell in the grass hibernating season. A high water table near the sea also pushes seawater into conventionally landscaped ground, but it cannot enter an EPIC profile.
On 28 December, eleven days after turfing, soil salinity read 0.91 at about 25 cm deep, against the 0.1 to 0.4 recommended for turf. The cause was unwashed sand and too much fertiliser. The system flushed itself: the water level was raised until fresh water flooded most of the profile, then drained, taking the salt with it, with no modification or special equipment. Flushing ran on 29 and 31 December and 3 January, and on 4 January 2012 salinity read below 0.4.
The client's daily meter log shows 102 m³ added over 105 days on the 400 m² plot. Take out the 16 m³ removed for flushing and use comes to 2.05 L/m²/day. Also take out the 38 m³ used to charge the profile and it comes to 1.14 L/m²/day. The existing pop-up sprinklers at Al Fanateer use 20 L/m²/day, and the report states a saving of more than 80%. By 21 February 2012, roots had reached at least 20 cm.
Project record
- Client
- Royal Commission for Jubail & Yanbu (RCJY)
- Location
- Community Area, Danah Road × Danah 3, Jubail Industrial City, Saudi Arabia
- Monitoring
- Eng. Faisal Al Khatib, SATCO, main coordinator on behalf of the Royal Commission, with two Epic Green Solutions team members stationed in the Eastern Province
- Contract
- SATCO Contract No. 951-S24
- Area
- 400 m², planting type turf (carpet grass)
- Commencement / completion
- 10 to 17 December 2011; turf installed 17 December 2011
- Water source
- TSE
- Initial charge
- 19 m³ from lorry tanker plus 19 m³ from the main supply line, to saturate the sand profile
- Initial fertiliser
- 100 kg slow release 15-15-15 plus 10 kg slow release 20-20-20
- Target set by the client
- 50% water saving
- Water added
- Tanker 22.5 m³ · pump 79.5 m³ · total 102 m³
- Removed for flushing
- 16 m³
- Used for charging the profile
- 38 m³
- Water attributable to the plot, 105 days, 400 m²
- Less flushing: 86 m³, 2.05 L/m²/day · less flushing and charging: 48 m³, 1.14 L/m²/day
- Existing pop-up sprinklers at Al Fanateer
- 20 L/m²/day
- Salinity, 28 December 2011
- 0.91 at about 25 cm depth; 7 m³ added for soil leaching
- Flushing
- 29 December, 31 December (a further 9 m³ added) and 3 January
- Salinity, 4 January 2012
- Below 0.4, accepted as the optimum level for turf
- Rooting, 21 February 2012
- Roots to at least 20 cm; good progress on greening and rooting
- Soil activity at 10, 15 and 25 cm
- EPIC 0.22 / 0.33 / 0.65 · normal sprinkler system 0.04 / 0.07 / 0.06
Working on a project? Send us the drawings, the bill of quantities or the question.
Talk to usPublished by EPIC Total Water Solutions LLC, Reno, Nevada. Issued in the Middle East and North Africa by Xpitrade General Trading LLC.




